Grid Connection and Power Generation of Section I of Qinghai Wutumeiren Multi-energy Complementarity 700 MW Photovoltaic Project (Phase I)

Date: 2024 - 02 - 05    Fonts:[ Big Middle Small ]

On February 4, Section I of the Qinghai Wutumeiren Multi-energy Complementarity 700 MW Photovoltaic Project (Phase I) was fully connected to the grid.

The installed capacity on the AC side of the project is 200 MW in bid section I. The 540 Wp and above monocrystalline silicon bifacial double-glazed modules can be used as PV modules. 28 collecting power lines are used in the 700 MW photovoltaic field of Phrase 1, of which 8 are used in bid section I connected to the newly built 330kV booster station on the 35kV low-voltage side. After being boosted by a 330kV main transformer, one 330kV transmission line will be connected to the Kunlun Mountain 750kV collecting station.